Changing EV Charging Operators in Malaysia: A Commercial Handover Checklist

10 minutes ago
4 min read

Before changing EV charging operators, test one representative charger on the incoming platform and complete a real charging session from start to receipt. Keep existing hardware only if you can verify who owns it, who can reconfigure it and which functions still work. Set the cutover date after the incoming operator confirms the site’s licensing position, both operators agree who handles old payments and refunds, and drivers have a tested way to start a session.


Illustration of an EV and chargers in a commercial car park beside a pilot and staged cutover checklist.

Use this checklist once your site is preparing to switch providers. If you are still writing the tender, start with EvGuru’s OCPP and vendor lock-in guide. For the cutover, use the workplace access guide to plan re-enrolment and the charger uptime guide to set the monitoring handover.


1. Establish what the site can keep

Before the pilot, put the charger model, serial number, firmware and owner in one inventory. Ask who can release each unit from the outgoing platform, who can reconfigure it and when both teams can attend the test. Agree on the exit date, removal rights, fees and warranty responsibilities using the signed contract.


The Open Charge Alliance describes OCPP as the communication protocol between the charger and its management system. OCPP 2.0.1 is not backward compatible with 1.6. Even within 1.6, certification profiles differ, including support for smart charging and advanced security. Ask for the exact firmware, supported version and required functions on both sides before approving hardware reuse.


Decision

What you need to see

Keep the hardware

Written authority to reconfigure it and a passed test for each distinct setup.

Replace some chargers

An inventory that shows which models pass and a quote for the ones that cannot migrate.

Replace the whole installation

Written evidence that reuse is unavailable or that replacement better meets the site’s needs. Ask which electrical infrastructure can still be retained.

If you need replacements for some bays, size them to the parking pattern. For example, EvGuru lists its Guru Agility as a 30 or 40 kW DC option with app and RFID access. That is a replacement option to assess for short stays. Confirm the proposed configuration and site capacity before specifying it.


2. Assign licences, money and records before cutover

The Energy Commission’s EVCS licensing criteria identify the charge point operator as the applicant. Ask the incoming operator to confirm with the relevant regulator what authorisation is needed for your site and who will hold it. Keep that confirmation with your approvals and refer electrical or commissioning changes to a competent person under the EVCS guidelines.


Handover item

What to agree in writing

Historic transactions

Export session ID, connector, timestamps, kWh, charge, refund status and settlement references needed for reconciliation.

Refunds and open disputes

Name the operator that will handle pre-cutover transactions, its contact channel and the reporting cut-off.

Driver access

Decide which accounts or RFID cards need re-enrolment. Test any proposed transfer before promising it.

Driver communications

Give drivers the cutover window, access instructions, new support contact and where to get old receipts.

Keep financial reconciliation separate from driver enrolment. Share only the personal data required for the agreed purpose, confirm the authority for disclosure and agree how it will be secured and retained. See Malaysia’s Personal Data Protection Department guidance. Ask the outgoing operator how drivers can access old receipts without transferring their full account history.


3. Pilot one unit per distinct setup, then switch in batches

Group chargers by model, firmware, network setup and required features. Once the site confirms the required permissions and approvals, pilot one representative unit in each group. Agree who will restore the previous service if the pilot fails.


At the bay, check that the QR or app maps to the exact connector, the fee shown is correct and the session ends with the expected record. Where the site uses RFID, load management or roaming, add those functions to the acceptance script. Check each bay individually when it goes live.


Worked example: keep four of six bays open during the first batch

Assume a six-bay site can move two bays at a time, each batch takes 45 minutes, the outgoing operator can keep the other bays live, and the standby bays are unaffected by shared dependencies. Under those assumptions, a staged change takes 135 minutes across three batches and leaves four bays available during each batch. Compare that with one simultaneous 45-minute closure.


Illustrative plan

Effect on service

All six together

6 × 45 minutes = 270 unavailable bay-minutes. No bays available during the closure.

Two at a time

3 × 2 × 45 minutes = 270 unavailable bay-minutes. Four bays remain available in each batch if they stay independent.

Both plans take the same number of bay-minutes out of service under these assumptions. Staging preserves some charging access and limits the bays affected if a batch fails. If both operators depend on the same gateway, payment system or site controller, verify that split operation works before using this plan.


Go-live sign-off

  • Save the tested charger-to-bay mapping and name the person who signs off each batch.

  • Check that the displayed price, session record and receipt agree. Test the support channel as a driver would.

  • Replace the old signs and QR labels only when the corresponding bays are ready. Check each replacement label from the bay.

  • Watch the first live sessions and reconcile old and new settlements at the agreed cut-off. Name the person who can pause or reverse the migration.


Questions to resolve before you give notice

Can drivers keep using their existing RFID cards?

Possibly. Ask whether the incoming platform can enrol the exact card and revoke it independently. Test an approved and a revoked card. Sending a new enrolment link can be simpler when account or credential transfer is unavailable.


Who handles a session that crosses the cutover?

Agree in advance which platform records it and who issues the receipt or any refund. The simplest window is one with no active sessions on the bays being switched. Make the outgoing support route available for earlier sessions.


Can we keep the old QR labels?

Only if the new operator can verify that each label resolves to the correct live connector and shows the right rate and support information. Scan the physical label in front of each bay using a phone that has never charged there.