Where EV Chargers Can and Cannot Go in a Malaysian Car Park: the GPP EVCB Rules

13 hours ago
5 min read

The short answer

AC chargers up to 22kW can go on any indoor parking level in a Malaysian multi-storey building. DC chargers cannot: indoors they are limited to the ground floor and the first two upper parking levels, and in basement parking to the first level below ground only. Those limits come from the national planning guideline GPP EVCB and follow Bomba fire-safety guidance, so a basement DC plan will not get past your local authority.

What GPP EVCB actually is

GPP EVCB is the Planning Guidelines for Electric Vehicle Charging Bay published by PlanMalaysia (the federal Department of Town and Country Planning). It is written for state and local authorities, which is why it decides what your building submission can and cannot include. If you manage a condo, mall, office block or car park, this is the document your plan is read against.

It covers where bays may sit, how big they must be, how many a new development needs, and how long the local authority takes to approve them.

Where chargers can and cannot go

Location

AC up to 22kW

DC fast charging

Open-air or rooftop parking

Allowed

Allowed

Ground-floor indoor parking

Allowed

Allowed

Upper indoor parking levels

Allowed on every level

First two upper levels only

Basement, first level below ground

Allowed

Allowed

Basement, second level and deeper

Allowed

Not allowed

Beside stairs or emergency exits

Must not obstruct exit routes

Must not obstruct exit routes

Two things follow from this for a property manager. First, if your car park is mostly deep basement, your realistic plan is AC, not DC. Second, bay selection is a fire-escape question before it is an electrical one: a bay that blocks an exit route will be rejected even if the power is right there.

How many bays a new development must provide

Requirement

What the guideline says

New multi-storey residential or commercial

At least 2% of total parking spaces as EV charging bays

New residential

At least one EV charging bay in visitor parking

New commercial

At least one disabled-friendly (OKU) EV charging bay

New residential and commercial

At least one electric motorcycle charging bay per building

Existing developments

Number based on demand — a recommendation, not a requirement

Standard bay size

2.5m wide x 6m long

OKU bay size

Add 1m to the width

That last line matters most to existing buildings. Nothing forces an existing condo or office block to install anything. Which means the decision sits entirely with your committee or owner, and the usual trigger is residents or tenants asking.

Approval timelines

The guideline sets the local authority's processing window at 7 days for AC chargers and 14 days for DC chargers. Those are the authority's days, not your project's. Supply confirmation from TNB, an ST-registered contractor, wiring, and the committee's own approval cycle are what actually set your calendar.

Permitted locations under the guideline are broad: strata and non-strata housing, industrial and commercial areas, institutions, petrol stations, and rest and service areas, outdoors, indoors or on rooftops. For how the electrical side is decided, see AC or DC EV charging for your building.

What people actually ask

These are real questions from Malaysian forums and news coverage, not invented ones.

The pattern across them is the same: residents assume the building has refused on fire-safety grounds, when in most cases nobody has checked which placement the guideline actually permits.

What this means for your building

  • Deep basement car park: plan AC. A DC proposal below the first basement level will not clear the guideline.

  • Mixed car park: put DC on the ground floor or the first two upper levels, AC everywhere else.

  • New development: budget the 2% bay requirement, the visitor bay and the OKU bay into the parking layout now, not after approval.

  • Existing building: nothing is compulsory, so the question is demand and who pays, not compliance.

Which of those applies is a site question. EvGuru surveys the car park, reads the incoming supply and comes back with a bay plan that matches the guideline. See our EV charging solutions for car parks and businesses, our condo and apartment charging page, and completed work in our project portfolio.

Request a free site assessment: message EvGuru on WhatsApp.

Frequently asked questions

Can I install a DC fast charger in my condo basement?

Only on the first level below ground. GPP EVCB limits indoor DC placement to the ground floor and the first two upper parking levels, and in basements to the first level below ground, following Bomba fire-safety guidance. Below that, AC up to 22kW is the workable option.

Is there a limit on AC chargers in a multi-storey car park?

No level limit. The guideline places no placement restriction on AC chargers up to 22kW in multi-storey buildings, so they can be built on every indoor parking level. Bays still must not obstruct exit routes.

Does my existing condo have to install EV charging bays?

No. The 2% bay requirement applies to new multi-storey residential and commercial developments. For existing developments the guideline says the number should be based on demand, and calls that a recommendation rather than a requirement.

How long does local authority approval take?

The guideline sets 7 days for AC chargers and 14 days for DC chargers at the local authority. That window does not include TNB supply confirmation, contractor scheduling or your own committee approval, which usually take far longer.

How big does an EV charging bay have to be?

A standard bay is 2.5m wide and 6m long. A disabled-friendly (OKU) bay adds 1m to the width. New commercial developments must provide at least one OKU bay.

Which buildings are allowed to have EV charging bays at all?

Strata and non-strata housing, industrial and commercial areas, institutions, petrol stations, and rest and service areas. Bays may be outdoors, indoors or on rooftops.